Green Biotechnology Co., Ltd. (hereinafter referred to as Green Biology), the predecessor of Hangzhou Green Perfume Chemistry Co., Ltd. was established in 1999, is a national high-tech enterprise integrating production, research and development, marketing of biological spices.
In February 2009, the company started the relocation technology transformation project, relocating the original production base to the Jiandemamu-Nanfeng Hi-tech Industrial Park in Hangzhou. The total planning land of the new plant area is 530 mu, and the first phase project is 300 mu. The production system has been completed and put into production by the end of 2010.
The company's business purpose: honesty and trustworthiness; committed to the development of biological fragrance and related industries, sustainable innovation, green manufacturing, caring for employees, reputation worldwide.
The company will produce a large number of industrial organic waste gases in the daily production process. On April 21, 2018, we entrusted our company Huanen Environmental Protection Full Power to deal with its process waste gases and flue gases. After 63 days of equipment manufacturing and installation, debugging, improvement and environmental protection testing, it is now successfully completed. Our company Huatene Environmental Protection Co., Ltd. will show the case of the waste gas project to the public. Details are as follows:
Exhaust Gas Composition: Oily Water Vapor, Non-Methane Total Hydrocarbons
Time: 2018/4/21, the agreement of Commission for waste gas treatment was reached
Exhaust air volume: 15000m3/h
Engineering Category: Environmental Protection Organic Waste Gas Treatment Project
Equipment selection: condensation cooling + alkali spraying + defogging + plasma degreasing fume + fan
Construction Unit: Suzhou Huaene Environmental Protection Technology Co., Ltd.
Client Unit: Hangzhou Green Biotechnology Co., Ltd.
Construction site: Jiande Mamu Development Zone, Hangzhou, Zhejiang Province
Project Description: Our company adopts condensation cooling +
alkali spraying + plasma degreasing fume. The purifying rate of organic
waste gas reaches 97% after environmental protection testing, and the
duration of the project is 33 days.
Project Leader: Manager Wang Jiansong
Business telephone: 13291195999